about the wheel

the engineering

The various parts of The Falkirk Wheel were actually constructed and assembled, like one giant Meccano set, at Butterley Engineering’s Steelworks in Derbyshire. A team there carefully assembled the 1,200 tonnes of steel, painstakingly fitting the pieces together to an accuracy of just 10 mm to ensure a perfect final fit.

In the summer of 2001, the structure was then dismantled and transported on 35 lorry loads to Falkirk, before all being bolted back together again on the ground, and finally lifted by crane in five large sections into position. The total 600 tonne weight of the water and boat filled gondolas imposes immense and constantly changing stresses on the structure as it turns around the central spine. Normal welded joints of steel would be susceptible to fatigue induced by these stresses, so to make the structure more robust, the steel sections were bolted together. Over 15,000 bolts were matched with 45,000 bolt holes, and each bolt was hand tightened.